PALMER ROAD BRIDGE UPDATE

We are almost at the completion of phase one:

September 27, 2019: Stage 1 will be completed and Phase 2 will begin. The road closure will reverse and the current sidewalk that is closed will reopen and the south sidewalk will close.

November 27, 2019: The day before Thanksgiving the bridge will be reopened for two-way traffic.
North side sidewalk will remain open - south side sidewalk will remain closed.

NOTE: The stone facing on the bridge WILL BE reattached but dependent on temperature will determine when that will take place