Friday, September 20, 2019

News from Westchester County Legislator, Gordon Burrows, 15th District.

Dear Neighbors,

PALMER ROAD BRIDGE UPDATE

We are almost at the completion of phase one:

September 27, 2019: Stage 1 will be completed and Phase 2 will begin. The road closure will reverse and the current sidewalk that is closed will reopen and the south sidewalk will close.

November 27, 2019: The day before Thanksgiving the bridge will be reopened for two-way traffic.
North side sidewalk will remain open - south side sidewalk will remain closed.

NOTE: The stone facing on the bridge WILL BE reattached but dependent on temperature will determine when that will take place

Best,

Gordon A. Burrows

No comments:

Post a Comment

Westchester Insider: Political Advertisement: Democrat Adeel Mirza for Westchester County District Attorney.

V ote for Adeel Mirza Democrat for Westchester County District Attorney in the Democratic Party Primary on June 25th. Adeel Mirza; Experienc...